Sembcorp Green Infra's build queue doubled in 2 years
Capacity running and under construction at 31 March, in MW and MWh. Under construction went from 2,030 to 4,040 while running capacity grew a third.
Sembcorp Green Infra's build queue doubled in 2 years
Capacity running and under construction at 31 March, in MW and MWh. Under construction went from 2,030 to 4,040 while running capacity grew a third.
MW AND MWH
RunningUnder construction
The prospectus adds MW of wind and solar to MWh of batteries. FY26's 4,040 under construction is 2.61 GW of wind and solar and 1.43 GWh of batteries.
Sembcorp Green Infra, draft abridged prospectus, 26 August 2026: key performance indicators · Mar 2024 to Mar 2026