Adani Power won the Bihar plant first, then Adani Energy its line
Adani Power won the Bihar plant first, then Adani Energy its line
Adani Power release, 29 August 2025; REC Power Development and Consultancy RFP, 29 July 2026; Adani Energy Solutions NSE filings, 19 and 22 November 2026 · Aug 2025 to late 2028
Share this chart
The numbers
Embed it on your site
The code carries a credit line that links back to this page. Keep it with the chart.
From the insight
Sources
- Adani Power, media release of 29 August 2025: LoA for 25 years at Rs 6.075 per KWh
- REC Power Development and Consultancy, RFP for evacuation of power from 3x800 MW STPP Pirpainti, 29 July 2026, page 1
- Adani Energy Solutions, NSE filing of 22 November 2026, page 3: VPTL registered on August 24, 2026; page 2: paid-up capital Rs. 5 Lakh
- Adani Energy Solutions, NSE media release of 19 November 2026, page 2: wins the project, ~Rs 500 cr a year
- Adani Energy Solutions, NSE media release of 19 November 2026, page 2: delivered by the last quarter of 2028