CleanMax's Andhra plan against what its finished plants cost to build
CleanMax plans to invest ₹50,000 crore in Andhra, 3.3x what its plants cost
On 12 November, CleanMax told the stock exchanges it proposes to invest nearly ₹50,000 crore in Andhra Pradesh. That is 3.3x the ₹15,182 crore that all its finished plants cost to build, as of 30 September. The deal is a memorandum of understanding (MoU), a signed statement of what CleanMax and the state mean to do. The customer it would serve has signed only an MoU too.
CleanMax builds solar and wind farms and sells their power to companies such as Amazon, Google and Meta under long contracts. Its farms can produce 3.6 GW today.
The plan is 3 GW of wind and solar and 1 GW of pumped storage within 5 years. Pumped storage pumps water uphill when power is spare and lets it flow back down through turbines when power is needed. The power would run a 2 GW park of AI computers in Kurnool district. Neysa, an AI cloud company, would use 1 GW of it. At least 1.5 GW of the new farms is meant to be ready by 2029.
8 days earlier, on the call about its quarterly results, managing director Kuldeep Jain gave a rule of thumb. Each gigawatt of data centres needs about 3 GW of wind, 3 GW of solar and 2.5-3 GW of storage, costing about ₹40,000 crore. By his own rule, the Andhra plan has half the wind and solar that Neysa's share alone would need, and it costs more.
The release does not say how the money splits. At the building costs per MW in CleanMax's own results presentation, that much wind and solar would cost about ₹14,400 crore, our estimate. That leaves about ₹35,600 crore for storage, batteries and a power network of its own inside the park.
CleanMax pays for its plants with loans and its own earnings. It already owes ₹13,838 crore more than it holds in cash. So this plan depends on another plan, Neysa's AI park, which also rests on an MoU. Until both become firm contracts, the pledge is an intention. Who makes money at each step of India's sun and wind is in our Macro Brew.
CleanMax's Andhra pledge is 3.3x what its plants cost
The Andhra plan next to CleanMax's accounts at 30 September 2026, in ₹ crore. The plan is bigger than everything it has built so far.
₹ CRORE
Plants built: the gross block, at cost before depreciation. Being built: capital work in progress. The pledge is an MoU.
Clean Max Enviro Energy Solutions, BSE filings: Andhra MoU press release (12 Nov 2026) and Q2 FY27 investor presentation (3 Nov 2026) · 30 Sep 2026 and 12 Nov 2026
CleanMax plans 3 of the 12 GW its own rule says the park needs
Wind and solar, in GW: what CleanMax's managing director says AI data centres need, and what the Andhra plan holds. The plan has a quarter of it.
GW OF WIND AND SOLAR
Per the call, the rule also needs 2.5-3 GW of storage and covers about 75% of the power used. 2 GW park: 6 x 2.
Clean Max Enviro Energy Solutions, BSE filings: Q2 FY27 earnings call transcript (6 Nov 2026) and Andhra MoU press release (12 Nov 2026) · Nov 2026
Wind and solar take under a third of CleanMax's ₹50,000 crore
The Andhra plan in ₹ crore, with 3 GW of wind and solar priced at CleanMax's own building costs; our estimate. The rest pays for storage and power lines.
₹ CRORE
- 3 GW of wind and solar, at CleanMax's own costs14,370 28.7%
- Everything else: storage, own power network35,630 71.3%
Wind and solar: 2,100 MW x ₹3.5 crore + 900 MW x ₹7.8 crore, before soft costs of 5-7%. An estimate, not a figure in the release.
Clean Max Enviro Energy Solutions, BSE filings: Andhra MoU press release (12 Nov 2026) and Q2 FY27 investor presentation (3 Nov 2026); our working · Nov 2026
Sources
- Clean Max Enviro Energy Solutions, BSE filing of 12 November 2026: press release on the MoU with Andhra Pradesh (PDF)
- Clean Max Enviro Energy Solutions, BSE filing of 6 November 2026: Q2 FY27 earnings call transcript, call of 4 November 2026 (PDF)
- Clean Max Enviro Energy Solutions, BSE filing of 3 November 2026: investor presentation, Q2 FY27 (PDF)