of Seamec's diving support vessels stopped work on 18 November
3 Seamec ships stopped work on the same day
On 18 November, Seamec told the exchanges that 3 of its 7 diving support vessels had stopped work: 2 broke down and 1 went for planned repairs. The same day it won a $10.77mn order.
These ships carry divers and their gear out to sea to repair undersea pipelines and oil platforms, much of it for ONGC. Seamec is paid by the day or by the job, so a ship off hire (out of paid service) earns nothing, and Seamec bears the cost of a breakdown.
Seamec Princess pulled out with a technical snag at 02:30. It had sailed 10 days earlier for ONGC's undersea pipeline replacement project PRP-X, where Seamec's share is a fixed $26.14mn. The $10.77mn order is more work on that same project.
Seamec Anant went off hire at 17:00 with a technical issue, 4 weeks into a charter worth about $55mn over about 1,225 days, or about $44,900 a day.
Seamec bought Anant in July for $70mn from oil and gas services company HAL Offshore, its promoter (the parent that owns 70.77% of Seamec), then hired it back to HAL for ONGC work. Seamec calls both deals arm's length, priced as between strangers.
The third ship, Seamec Agastya, also works for HAL, at $25,000 a day. It left for planned repairs and its yearly survey. But it had already broken down 5 times this year, off hire for about 30 days.
Seamec told analysts on 4 November it allows 2 to 3 days of breakdowns a ship. Agastya has lost 10x that this year. Charters pay only while ships work: with Anant and Agastya both out, about $70,000 a day of hire stops.
Seamec Agastya broke down 5 times in 2026
DAYS OFF HIRE
The June stop is counted from the start of 15 June; the filing gives no hour. The 18 November stop is planned and not counted.
Seamec, NSE off-hire and on-hire filings for Seamec Agastya, January to September 2026 · Jan to Sep 2026
Seamec Anant broke down 4 weeks into its charter
Seamec, NSE filings of 21 July, 31 August, 14 October, 21 and 22 October and 18 November 2026 · Jul to Nov 2026
Sources
- Seamec, NSE filing of 18 November 2026: Seamec Princess pulled out of the field with a technical snag (PDF)
- Seamec, NSE filing of 18 November 2026: Seamec Agastya off hire for planned repairs and annual survey (PDF)
- Seamec, NSE filing of 18 November 2026: letter of award from POSH India Offshore for PRP-X subsea work, with annexure (PDF)
- Seamec, NSE filing of 18 November 2026: Seamec Anant off hire with a technical system issue (PDF)
- Seamec, NSE filing of 7 November 2026: L&T's letter of award for PRP-X to the Seamec and POSH consortium, with annexure (PDF)
- Seamec, NSE filing of 8 November 2026: Seamec Princess leaves Mumbai for PRP-X (PDF)
- Seamec, NSE filing of 21 July 2026: agreement to buy Seamec Anant from HAL Offshore for USD 70 million, with annexure (PDF)
- Seamec, NSE filing of 31 August 2026: addenda to the Seamec Anant purchase agreement, new ready and cancelling dates (PDF)
- Seamec, NSE filing of 14 October 2026: Seamec Anant taken over from HAL Offshore at Kakinada (PDF)
- Seamec, NSE filing of 21 October 2026: Seamec Anant chartered to HAL Offshore for ONGC work, with annexure (PDF)
- Seamec, NSE filing of 22 October 2026: Seamec Anant on hire from 21 October (PDF)
- Seamec, NSE filing of 4 December 2025: Seamec Agastya chartered to HAL Offshore at USD 25,000 a day, with annexure (PDF)
- Seamec, NSE filing of 13 January 2026: Seamec Agastya out of the field for a technical reason (PDF)
- Seamec, NSE filing of 17 January 2026: Seamec Agastya back on hire (PDF)
- Seamec, NSE filing of 9 April 2026: Seamec Agastya out of the field for a technical reason (PDF)
- Seamec, NSE filing of 21 April 2026: Seamec Agastya back on hire (PDF)
- Seamec, NSE filing of 15 June 2026: Seamec Agastya off hire for a technical reason (PDF)
- Seamec, NSE filing of 23 June 2026: Seamec Agastya back on hire (PDF)
- Seamec, NSE filing of 9 September 2026: Seamec Agastya off hire for a technical reason (PDF)
- Seamec, NSE filing of 10 September 2026: Seamec Agastya back on hire (PDF)
- Seamec, NSE filing of 16 September 2026: Seamec Agastya off hire for a technical reason (PDF)
- Seamec, NSE filing of 19 September 2026: Seamec Agastya back on hire (PDF)
- Seamec, BSE filing of 10 November 2026: transcript of the Q2 FY27 earnings call of 4 November 2026 (PDF)
- Seamec, BSE filing of 3 November 2026: Q2 and H1 FY27 investor presentation (PDF)