of Seamec's diving support vessels stopped work on 18 November

3 Seamec ships stopped work on the same day

Companies No. 215 19 November 2026 · 2 min read · By

On 18 November, Seamec told the exchanges that 3 of its 7 diving support vessels had stopped work: 2 broke down and 1 went for planned repairs. The same day it won a $10.77mn order.

These ships carry divers and their gear out to sea to repair undersea pipelines and oil platforms, much of it for ONGC. Seamec is paid by the day or by the job, so a ship off hire (out of paid service) earns nothing, and Seamec bears the cost of a breakdown.

Seamec Princess pulled out with a technical snag at 02:30. It had sailed 10 days earlier for ONGC's undersea pipeline replacement project PRP-X, where Seamec's share is a fixed $26.14mn. The $10.77mn order is more work on that same project.

Seamec Anant went off hire at 17:00 with a technical issue, 4 weeks into a charter worth about $55mn over about 1,225 days, or about $44,900 a day.

Seamec bought Anant in July for $70mn from oil and gas services company HAL Offshore, its promoter (the parent that owns 70.77% of Seamec), then hired it back to HAL for ONGC work. Seamec calls both deals arm's length, priced as between strangers.

The third ship, Seamec Agastya, also works for HAL, at $25,000 a day. It left for planned repairs and its yearly survey. But it had already broken down 5 times this year, off hire for about 30 days.

Seamec told analysts on 4 November it allows 2 to 3 days of breakdowns a ship. Agastya has lost 10x that this year. Charters pay only while ships work: with Anant and Agastya both out, about $70,000 a day of hire stops.

A table of Seamec's 4 filings of 18 November 2026: Seamec Princess broke down at 02:30 on the PRP-X pipeline project, Seamec Agastya went off hire at 04:00 for planned repairs, POSH India Offshore awarded Seamec about $10.77mn of PRP-X work at 12:01, and Seamec Anant broke down at 17:00 on its charter to HAL Offshore.

Seamec Agastya broke down 5 times in 2026

Bars for 5 breakdowns of Seamec Agastya in 2026: 4.3 days in January, 12.2 days in April, 8.0 days in June, and 2.4 and 3.4 days in September, about 30 days in all.

DAYS OFF HIRE

The June stop is counted from the start of 15 June; the filing gives no hour. The 18 November stop is planned and not counted.

Seamec, NSE off-hire and on-hire filings for Seamec Agastya, January to September 2026 · Jan to Sep 2026

Seamec Anant broke down 4 weeks into its charter

A timeline of 5 dates: on 21 July 2026 Seamec agrees to buy Seamec Anant from HAL Offshore for $70mn; on 31 August the delivery dates move; on 14 October Seamec takes the ship, 1 day before the cancelling date; on 21 October it is chartered back to HAL for about $55mn over about 1,225 days; on 18 November it goes off hire with a technical issue.

Seamec, NSE filings of 21 July, 31 August, 14 October, 21 and 22 October and 18 November 2026 · Jul to Nov 2026

Sources