A Saudi client cancels Ashoka Buildcon's ₹846 crore hotel job

Companies No. 226 19 November 2026 · 1 min read · By

Ashoka Buildcon's share rose 6.7% on 18 November as the Nifty 50 fell 0.6%, after it bid lowest for a ₹1,465 crore highway job. A day later it said a Saudi client had cancelled its ₹846 crore hotel job.

Ashoka builds roads, bridges, railway lines and power lines, mostly for governments, and is paid as it builds. So investors watch its order book, the work won but not yet done: ₹15,964 crore on 30 September.

Bidding lowest, called L-1, is not a contract yet: NHAI, the national highways authority, still has to accept it. Ashoka counts L-1 bids anyway. Its ₹17,222 crore order book on 6 November included one on the next stretch of the same expressway, accepted on 9 November.

The Saudi job had gone further. In February Ashoka's Saudi unit and a local partner won a hotel in Diriyah, Ashoka's share ₹846 crore. Diriyah Company (the developer of a heritage and tourism district near Riyadh), part of Saudi Arabia's state wealth fund, has now cancelled it for internal reasons.

It was still ₹822 crore, or 5.1%, of the September order book. So the cancellation takes back more than half of the new road, leaving ₹643 crore net.

The share rose on a road Ashoka has not yet been given, and the hotel it had been given is gone. An order book is a list of promises, and promises can be taken back.

Ashoka Buildcon's lost Saudi hotel takes back half its new road

A waterfall from an order book of 16,356 crore, up 866 crore for package 9 of the Vadodara-Mumbai Expressway to 17,222 crore on 6 November, down 822 crore for the cancelled Saudi hotel and up 1,465 crore for package 8, a lowest bid not yet accepted, to 17,865 crore.

Ashoka Buildcon, Q2 FY27 results presentation (6 Nov 2026) and filings of 17 and 19 Nov 2026 · 30 Sep to 19 Nov 2026

The cancelled Saudi hotel was 5.1% of Ashoka Buildcon's order book

₹ CRORE

  • Saudi hotel (now cancelled)822 5.1%
  • Everything else15,142 94.9%
A bar of 15,964 crore of work in hand, with a thin slice of 822 crore for the Saudi hotel that has now been cancelled and 15,142 crore for everything else.

Ashoka's 49% share of the job was ₹846 crore when won in February; ₹822 crore was left in the September order book.

Ashoka Buildcon, Q2 FY27 results presentation, 6 Nov 2026, and NSE filing of 19 Nov 2026 · As on 30 Sep 2026