₹20.02 lakh cr to ₹17.87 lakh cr

Spending logged on big central projects, January and October 2026

Central projects show ₹2.15 lakh crore less spent than January

Economy No. 319 26 November 2026 · 1 min read · By

MoSPI, the statistics ministry, says big central projects had ₹17.87 lakh crore spent on them by October 2026, 46.88% of their cost. In January its report showed ₹20.02 lakh crore spent.

So the government spent ₹2.15 lakh crore less? No. Money spent cannot be unspent. The report counts only ongoing projects of ₹150 crore or more, so a finished project leaves the list with its spending, and new ones keep joining.

Railways show it best. Railway projects on the list had ₹6.99 lakh crore spent in January and ₹1.86 lakh crore by August, as their count fell from 249 to 147.

Then September added 57 railway projects. Spending on the whole list rose ₹1.40 lakh crore that month, and railways alone added ₹1.76 lakh crore.

The list does show where projects stand. 649 are over 80% built, but only 326 have spent over 80% of their cost. MoSPI puts early spending down to upfront costs and gives no reason why work runs ahead of money near the end.

So the 47% spent says more about which projects are on the list than about how fast India is building. Read month against month, the totals can even show money going backwards, as January to October did.

Big central projects show less spent in October than in January

₹ lakh crore, 2026

Paired bars by month: cost ₹39.25, ₹33.60, ₹37.56 and ₹38.11 lakh crore and money spent ₹20.02, ₹16.33, ₹17.73 and ₹17.87 lakh crore in January, August, September and October 2026.

₹ LAKH CRORE

Cost of projects on the listMoney spent on them

MoSPI, flash reports on central sector infrastructure projects, January, August, September and October 2026 · Jan to Oct 2026

Railway projects left the list by August, then came back

₹ lakh crore, 2026

Paired bars for railway projects: cost ₹8.46, ₹3.14, ₹7.21 and ₹7.38 lakh crore and money spent ₹6.99, ₹1.86, ₹3.62 and ₹3.73 lakh crore in January, August, September and October 2026.

₹ LAKH CRORE

Cost of railway projectsMoney spent on them

MoSPI, flash reports on central sector infrastructure projects, Annexure I, Ministry of Railways · Jan to Oct 2026

Near the finish, twice as many projects are built as paid for

Projects by stage, October 2026

Paired bars of project counts by stage: built 429, 239, 222, 323 and 649 and paid 478, 299, 381, 378 and 326 in the 0-20%, 21-40%, 41-60%, 61-80% and 81-100% bands.

PROJECTS

BuiltPaid

Built is work done; paid is money spent against the project's cost.

MoSPI, flash report on central sector infrastructure projects, October 2026, Figure 1 · Oct 2026