Wind and solar take under a third of CleanMax's ₹50,000 crore

The Andhra plan in ₹ crore, with 3 GW of wind and solar priced at CleanMax's own building costs; our estimate. The rest pays for storage and power lines.

Wind and solar take under a third of CleanMax's ₹50,000 crore

The Andhra plan in ₹ crore, with 3 GW of wind and solar priced at CleanMax's own building costs; our estimate. The rest pays for storage and power lines.

₹ CRORE

  • 3 GW of wind and solar, at CleanMax's own costs14,370 28.7%
  • Everything else: storage, own power network35,630 71.3%
A bar for the ₹50,000 crore pledge: about ₹14,370 crore for 3 GW of wind and solar at CleanMax's own costs, and about ₹35,630 crore left for everything else.

Wind and solar: 2,100 MW x ₹3.5 crore + 900 MW x ₹7.8 crore, before soft costs of 5-7%. An estimate, not a figure in the release.

Clean Max Enviro Energy Solutions, BSE filings: Andhra MoU press release (12 Nov 2026) and Q2 FY27 investor presentation (3 Nov 2026); our working · Nov 2026